

The hillside was considered too difficult to build. A combination of factors—
the steep grade, limited access, absence of parking and no flat spot to store
materials or stage supplies on—kept the land vacant. But the view toward
the north made the project compelling. Large expanses of glass could
be installed without worrying about direct sunlight or the need for shade.


The steep site became a kind of litmus test for subcontractors. RJC established
early on that we would not pay a premium because of the site’s challenges.
We located several other construction projects nearby to take our grading soils,
and others to import their soils when it came time to back-fill the basement
walls. Grading after the basement excavation involved heavy digging equipment
perched upslope on a tight ridge.

Access was a constant issue. The small lot and uphill location left little room
to maneuver. The earthen ramp was installed and altered throughout the
foundation phase, depending on the equipment needed. We outlined our
approach prior to the bidding so that the ramp work was a fixed cost for our
grader and never an issue when modifying or relocating it was required.

We have completed many projects with our soils engineer, Grover-Hollingsworth
& Associates, Inc., and have established a productive working relationship
based on the mutual understanding that we are both interested in providing the
highest quality work. Every site has unique soils that require unique solutions.
This particular site contains a high quantity of shale, which, while good for
drilling and excavating, is porous. Water seeps right through and begins to
attack foundations. This means that the basement waterproofing is of primary
importance, and the perimeter drainage systems at the foundation and retaining
walls will be like little streams. To accommodate the flow, we doubled the
basement wall waterproofing and increased the diameter of perimeter drains
from four to six inches.


On each job there seem to be two or three subcontractors that shine and become
the project All-Stars. On this project I would have to put Rebar-Ranch from
Santa Paula at the top of the list. The owner, Jay Guertin, hand-built this rig
from a discarded Bobcat tractor chassis specifically for tight-access hillside
foundation work. It is so small that it must be operated by remote control.
Despite being skinny, this rig can drill to twenty-five feet on a slope up to a
forty-five degree angle. Aside from his MacGyver-like ingenuity, Guertin’s
optimistic attitude is a prerequisite to digging hillside foundations. He’s drilling
a three-foot-diameter by twenty-foot-deep caisson.


To the architect’s credit, the builders for his custom homes are brought
in early. Using his design parameters, we initiate discussions of constructability,
cost, and schedule. We discuss the foundation system at the outset, during
the schematic design phase. A hybrid caisson/grade beam system turned
out to be an efficient and cost-effective solution since the soil was
quite stable with little heavy rock. We were able to use a foundation
system without oversize caissons or excessive grade beams and cumbersome
structural slabs.

We were able to “claim” a patch of flat landscape on the steep site by adding a
retaining wall on the downslope edge of the property. The client had to weigh
the cost of the retaining walls against the value of level land on this property.
We also priced the work if done at a later date, after the house was complete.
It turned out to be an easy decision; the level ground also gave us a staging
area (albeit a small one) on the north side of the building.

Phasing the project’s various elements usually comes down to budget and
schedule. More often than not, we prefer to leave pools, spas, and water
elements out until we are well into the project. On Redelco, however, we
decided to incorporate the pool and spa into thefoundation work. We made
this choice not only because of limited site access, but also because we
received better pricing by grouping all of our caisson work together.


Again, we must remain agile when challenges present themselves. This is not
the preferred equipment for setting steel columns. However, for structural
reasons, the steel columns had to be deeply embedded into the caissons and long
periods of crane time were needed to hold columns in place while the temporary
shoring was installed. The “Grade-All” forklift gave us both easier access and
a much lower hourly rate than a conventional crane setup.

Some of the more satisfying moments of the project occur when we start to
recognize the architect’s vision in spatial terms. Although the column is
temporarily shored up, awaiting the concrete pour, we begin to see how
Scarpa has framed the living room view. The building begins to claim the site.


Something that’s often overlooked in concrete work is the skilled carpentry.
The quality of carpentry for the foundations easily matched the carpentry for
the framing of the building. The concrete formwork is hard enough, but is a
genuine test when there are few benchmarks to work from. Often we are working
from a surveyor’s point a hundred feet away. All of our north-south foundations
had multiple steps with grade.

All of the rebar for this job was cut and fabricated in the field due to the lack
of staging areas and restricted site access.

As the concrete slab formwork and rebar is set for the cantilevered floor we get
new perspectives on the site. We have more than three times the weight in
rebar steel than we do in the steel columns and beams.


A bed of clean three-quarter-inch gravel laid against the basement wall
allows any subterranean water to flow through a vertical drainage board into
subterranean drains, and then quickly off-site.

Working with exposed concrete is one of the more challenging tasks a builder
faces. The foundation carpentry work goes from merely holding and forming the
cement while it cures, to a high-profile finish that emerges from the basement
to become the exterior shell of the building. At this point, the location of every
board and support brace is key to attaining the design result we desire. Working
with Scarpa on previous projects proved invaluable here, since we understand
his vocabulary and have a sense of what is important to him. We are constantly
trying to put the effort and money where you’ll see it, and where it matters most.


Modern residential architecture often involves the introduction of commercial
and industrial building techniques. We strive to be at the cutting edge of these
technologies, using various systems and techniques in innovative ways when
appropriate. Whether door and window, heating and air-conditioning, structural
systems, or hardware, the architect’s choices should not necessarily be limited
to “residential” products and technologies. We are using a concrete shoring
system designed for parking garages to form the sunken concrete living room
floor above.


As the basement concrete formwork is removed, once again, Scarpa’s intentions
are revealed and new opportunities arise. The opening in the basement ceiling
for the stair is also considered a light well and will influence the design of the
staircase. The handrails and treads are revised to be made more porous, allowin
for additional direct and indirect light to filter into the basement. One of our
goals is to provide an open atmosphere for the architect’s creative process
throughout the building process. As long as we are watching the budget and
schedule, I find it critical to the success of a design to allow design latitude
during the construction process.

Finely crafted architecture is often revealed in how well similar or different
materials are joined together. Unlike traditional architecture, which uses the
convenience of “trim” (casement, baseboard, or crown molding) to hide the
joints between elements and materials, modern architecture exposes itself in
a reductive manner. This seemingly simple slab-meets-wall detail is more than
meets the eye. We must align the new formwork pattern with the existing
pattern of the wall. Not difficult or obvious, unless we miss it.


Few things are as gratifying as seeing the building grow on the site. Again, we
begin to see the intent for the second floor come to light, and this will influence
everything from window location to furniture layout, which in turn will impact
electrical and lighting decisions.

From the second floor, views of the valley and mountains as well as sight lines
within the house begin to emerge. The photo was taken looking from the master
bedroom to the living room below.

A steel beam sitting on the second story floor, awaiting installation. Generally,
I am not inclined to run a job sequentially by completing one phase and then
moving to the next. Although some subcontractors disagree with this view, I find
it more productive to merge phases and work concurrently. We will often have
concrete, steel, and wood framing subcontractors running side by side for weeks.
A not-so-subtle request of our steel installer at this moment was to have the
wood framer slow down. The start of a job somehow never has the same urgency
as the last few frenzied weeks.


Although the building envelope is designed, and we’re not expecting any major
revisions, our weekly meetings are vital during the framing stages. Now we can
easily raise or lower windows and adjust or even relocate partitions to make
subtle changes and refinements to the interior spatial experience.

Regardless of the size of the project, material waste and run-off is a constant
concern when constructing a building. Our oceans often bear the brunt of sloppy
construction practices such as slurry from concrete and painting cleanup.
RJC Builders observes sustainable practices in building. We maintain a diligent
“Storm Water Prevention Plan” that is stricter than required by our local
agencies. Consistent sandbagging and monitoring of the perimeter is one
aspect of the plan.

Upon seeing the light strike the concrete wall (just to the left of the ladder),
Scarpa had the idea of placing ten small colored glass cylinders in the wall,
to allow light to pass through.

On my weekly job site walk-throughs, I touch on three primary aspects of the
project: quality, cost, and schedule. As we move from room to room the question
in my mind is: “What could we be working on here that we’re not?” The minute
the steel frame is installed, I want to see the tracks for the oversize glass doors
that fill these bays. In reality, we have been working off-site on these tracks and
doors for months in anticipation of this setup. Our progress on any given day is
dictated by our planning efforts weeks, sometimes months, prior to installation.


Raking light against a board-formed concrete wall; the building begins to find
its voice as some of the final pieces emerge from the seeming disarray of
construction. Sometimes on a site I feel like the first person to read a great
poem. The shadow of the cast-in-place concrete beam above provides shade
for the front entrance door just to the left of the steel column.

There were no structural drawings for this cantilevered shelf, which will
eventually hold a sink and a barbecue. After pouring nearly seven hundred
cubic yards of concrete for the foundations and walls, our subcontractor
didn’t even need to ask.

As the interior partitions begin to go up, we’re not afraid to let some of the
non-structural wall articulation lag slightly behind. The two by six projections
here start to outline the alcove for the flat-screen TV, for which we have not yet
received exact specifications. By installing enough framing to give the architect
a physical idea of the object, he can alter it in the field without the additional
cost of removing and replacing completed work.

TGIs, PARA LAMs, OSB, and CDX Stuct 1—this alphabet soup of wood-framing
members and sheathing is growing as building codes become stricter and stricter
each year, especially as it pertains to seismic strength requirements. As
cumbersome as building codes and the permitting process can be, we get safer
and more substantial buildings because of them.

The cantilevered beam in this wall meant GK Plumbing had to run the vent line
along a circuitous route around the beam and posts, but we didn’t hear a single
complaint.

I gained great respect for the working relationship between the structural
engineer and the architect on this project. The engineer, Gordon Polon, and
Scarpa not only solved the structural requirements in an elegant manner
with slender, well-spaced steel columns set back from exterior enclosures,
but they did it while making three separate buildings that sit within inches of
each other. The main house is split into two volumes, separated by glass walls
and skylights. The third structure is lifted twelve feet off the ground and
connected by a lightweight perforated-steel bridge. Here, we see the three
roofs with their narrow slots of separation.

Not a bad place to go to work. The roof diaphragm plywood installation is
complete and waiting for a city inspector prior to roofing. A box of shear nails
is left behind as confirmation for the inspector that we have used nails that are
the proper length and thickness.The easier we make his job, the easier he’ll
make ours. The roof required seventy-six sheets of plywood with one hundred
and twenty-eight nails each. That is almost ten thousand nails.

Experimentation makes it all worthwhile. I can’t imagine a project where all
the details, let alone form and space, are the same as the last one. This is one
of the pleasures of working on custom-built houses. Scarpa generally starts
with a clear idea of what he wants but is open to how we technically solve the
details of fabrication and installation. The location of the copper cladding for
the exterior skin of the building was established early, along with a price-per-
square-foot cost. Through samples such as this one, we refined the proper
proportions, joint sizes and connection details. The underlayment of a Grace
Ice/Water Shield was also resolved; should water infiltrate a seam, we have
a second layer of weather protection for the wood framing behind the
copper cladding.

It seems difficult to compete with the simple economics of prefabricated
fireplaces unless you have a memory of the real thing. In calculating the budget,
we earmarked the funds for a brick and concrete fireplace, but as we progressed
through foundation and framing the money was eyed as a possible line item cut.
Fortunately, it survived and became a centerpiece of the living room. Scarpa
had forms milled from dense foam on a CNC machine. Installed, the cast
concrete fireplace mantle and surround give the appearance of a billowing
curtain across the open hearth.

As we enter the last phase of construction, it becomes clear that the client has
not been editing his options list. The budget was tight to begin with and we
pushed it all the way to the end. As a means to helping get us back on budget,
we locate some unique tile at a terrific savings and acquire the exterior stone
directly from Mexico. I introduce the tile subcontractor to Andujar & Son Tile
Co. and allow the client to pay them directly, giving him my wholesale cost
without my fee while passing along the savings on material. Milton Andujar
(the “& Son”) thoughtfully coordinates his work shirt with our choice of tile.


I am forever cognizant that our efforts, at bottom, are geared to providing shelter.
Translation: Everything must be flashed to keep water out. At Redelco, Scarpa
elevated a utilitarian part of the project and combined several items into an
elegant and innovative architectural detail. The long flat portion provides the
terminal point for the built-up roofing, while the square channel-shaped piece in
the center is a scupper giving rainwater a low point to exit the roof.

Modern architecture doesn’t always leave much space for mechanical chases,
that is, a place to put all of the ducts, pipes, and cables. Here, we were given the
upper corner of a garage ceiling and it is immediately jammed with heating and
air conditioning ducts, gas lines, high voltage wiring, fire sprinkler lines, hot
and cold water, security, telephone, cable TV, computer, and AV lines. We added
a storage cabinet the same depth as the chase so that the chase was continuous
with the cabinet face and not a visual blight. Although not required structurally,
we clad the interior garage walls with plywood, making installation of storage
shelves or racks simple and flexible.


Many interesting innovations are taking place with building materials these days.
Materials are being reformulated and reverting back to simpler base ingredients.
Example: Fiberglass batt insulation, while still the industry standard due to cost,
is gradually being replaced by an old favorite—recycled cotton jeans. “R-30
Unfaced Ultra Touch Cotton Batts” are chemical-free and environmentally safe
both in terms of manufacturing and recycling. Also, workers are not exposed to
dangerous airborne fiberglass strands during installation.


After the drywall sheets have been installed inside or the paper and lath installed
on the exterior, the most critical aspect of the finishes begins, placement of the
bent or extruded metal shapes used to establish all corners, joints, changes in
plane, and terminations. The installation of these metals brings the rough
framing, which can vary a quarter inch over ten feet, into perfect plumb and
straight line. The work takes a combination of talent and great patience.
A standard drywall installation doesn’t require the application of a continuous
topping, or skim coat. However, we provide a final skim coat over all interior
drywall surfaces. The skim coat creates a museum-quality wall and assures that
no seams or fastener dimples will telegraph in the future. The skim-coated wall
is subtly different than naked drywall. The wall, while perfectly flat, will have
the slightest undulation and, I think, a greater sense of weight or mass.

The various trades working concurrently on flooring tile, the swimming pool,
exterior copper cladding, finishing the drywall skim coats, painting, cabinets,
fireplace flue, and handrails. The rollers for the large doors can be seen in the
track where the living room ceiling edge meets the sky; these doors have been
rough fit and are out being fine-tuned prior to installing the glass.

A critical topic at our weekly job meetings is scheduling. We start with a detailed
timeline for the entire project, and then each week our superintendent updates
a three-week schedule, which immediately allows us to see where we’re at in
terms of the overall schedule. Quality takes time, so I don’t make promises about
completing work early, but we always expect to run on schedule. When we get
to the final stage of the project, scheduling questions are always more pressing.
As a client begins to see the finished product for the first time, their enthusiasm
becomes palpable. They want to move in now! Unfortunately, it’s my duty to
remind them that the last ten percent is half the job.

“...so shines a good deed in a weary world...”
|